IE and GB NIR Estimation Model

Mathilde Daugy edited this page Feb 8, 2023 · 1 revision

Model Overview


The data fetched from EIRGRID Group is incomplete. The parser collects data for the following kinds:

  • Demand,
  • Wind production,
  • Electricity exchanges.

Generation data published by EIRGRID does not provide a full production breakdown.

Consequently, production for Ireland and Northern Ireland is estimated using the Mode Breakdown model. The estimation process is as follows:

  1. The parser collects wind production and unknown production. Unknown production is estimated as:

Demand + net exports - wind

  1. Unknown production is then broken down using data from SEAI or BRMS.
    • In the case of Ireland, unknown production is reallocated using a monthly production mix. This monthly mix is computed for the last three full years of data. This enables the capture of the different modes' seasonality.
    • For Northern Ireland, unknown production is broken down using an annual production mix.
Screenshot 2023-02-08 at 15 43 15

Figure 1: Monthly production mix to reallocate for Ireland

Screenshot 2023-02-08 at 15 44 02

Figure 2: Annual production mix to reallocate for Northern Ireland